Patna Metro Corridor 2: Underground Tunnelling Reaches 7.4 km of 7.8 km, Six Stations on the Stretch
Patna Metro has dug 7.4 km of the 7.8 km underground section on Corridor 2, leaving about 400 metres to go. The stretch runs from the Malahi Pakri ramp through Akashvani towards Rajendra Nagar, and carries six underground stations: Rajendra Nagar, Moin-ul-Haq Stadium, University, PMCH, Gandhi Maidan and Akashvani. Civil work is targeted for completion by October 2026, after which the systems stage starts, covering track laying, overhead electrical work, cabling and signalling. The 6.2 km priority stretch from Patliputra Bus Terminus to Malahi Pakri, with five stations, already runs.